Construction Updates – October 2024

Update as on 3rd October, 2024

Construction Updates – October 2024

Update as on 3rd October, 2024

Titlis - OC received till the 64th Floor
100%
Pilatus
51%
Zermatt
21%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis
Tower raft – 100% completed
Podium raft-100% completed.
Basement – B1 complete, LG complete, UG complete.
Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab.
Center core CC completed till 58th floor.
Tower 1 OC received 
P1 to P8 podium floors completed, typical floor completed upto terrace level. Terrace above swimming pool & elevation work in progress.
Center core area casting including LMR completed up to top level.
South & west side balance podium civil work up to P8 completed.
Drop off Area – 100% RCC work completed upto B1 to P7 level & P8 level-  90% RCC work completed.
Finishing work
1) Block work & Gypsum- 9th to 63rd floor completed , 64th floor in progress, 40th -51st gypsum work completed , 52nd above gypsum work 80% completed .
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed & 40th to 64th work completed.
3) Flat Toilet waterproofing work – 9th to 51st floor all flats work completed & 52nd  above floor work in progress 85% completed.
4) External Painting Single coat completed up to 61st floor.
5) Project lift LW1 & LW2  Installation & Commissioning completed, LW3 is now operational in full speed from UG to 51st floor. LW4A & LW1C is now operational in full speed from UG to 65th floor .
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress.  kitchen ducts completed up to 51st floor completed & 52nd to 64th work in progress ( 80% completed)
7) Typical lobby 9th to 40th floor work completed.41st to 51st floor work 90% completed & 52nd to 63th floor lobby tiling work 80% completed.
8) Mid landing servant toilet completed up to 39th floor , toilet commissioned from 9th to 51st floor work in progress.
9)Copper piping work completed in lobby area.
10) Marble flooring work in progress in sold flat up to 51st floor,  52nd & above floor work in progress.
11) Electrical conducting & Choke up clearing work completed up to 63rd floor.
12) Window Installation work 94% completed up to 39th floor, & 40th to 51st floor work 90% completed. 52nd above floor work in progress ( 80% completed)
14)Internal Railing work 96% completed up to 39th floor & 40th -51st work in progress. ( 90% completed) & 52nd above floor work in progress.
15) External railing work 95% completed till 39th floor , 40th to 51st work 90% completed & 52nd and above floor work in progress.
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress. ( 85% completed ) & PU work 75% completed.
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started.
22) Project water supply line work completed 100% & building water distribution system commissioned.
23) UG level triple height main entrance lobby & p8 level amenity area is operational
24) Project water supply line work completed & Building water distribution system commissioned
Pilatus
Tower raft -100% completed.
Basement – B1 complete, LG & UG complete,P1 to P7 slab casting done. STP installation work in progress .
Raft, Basements 1 to P8 level -100% RCC completed, 1st floor service area work completed, 10th to 39th B Slab level casting completed. & 40th slab work in progress  Core area slab completed till 44th floor and 45th level slab in progress.
Finishing work 1) Block work completed till 34th floor & 35th to 37th floor work in progress. common area block work in progress.
2) Gypsum work completed till 29th floor & 30th floor work in progress.
3) Water proofing completed from 9th to 23rd floor & 24th floor & above work in progress.
Plumbing work in progress.
Waterproofing work completed till 29th floor , 30th floor work in progress
Bathroom tiling work in progress.
FAPA typical lobby completed upto 29th floor
Firefighting lobby work in progress from 9th to 35th floor, flat area work from 9th to 29th in progress, riser work 9th to 34th floor completed
Electrical conducting work from 9th to 33rd floor completed.
Zermatt
Excavation work
Excavation work completed
shore piling & capping beam work completed, soil retention work is in progress
Excavation work 100% completed.
Inclined rock anchoring 1st ,2nd & 3rd level work completed.
Tower c raft casting completed including non tower area
B1 & B2 slab work completed , LG slab work in progress