Construction Updates -July 2025
Update as on 2nd July, 2025
Construction Updates – June 2025
Update as on 12th June, 2025
% mentioned above is the current demand due as per the construction linked payment schedule
Tower Name | Floor Details | Detailed Updates |
---|---|---|
Titlis | Â OC received |
Blockwork & Gypsum: Toilet Waterproofing: Marble Flooring: Window Installation: Internal & External Railings: Internal railing work is 90% complete. External railing work is 95% completed from the 20th to 64th floor. Fire Fighting System: Completed from 9th to 39th floors (excluding select flats). Work on podium levels is 85% complete. 40th to 64th floors are fully done. Lobby Electricals: Typical lobby light fitting installation is completed. Copper piping work in lobby areas is completed. Electrical Conducting & Choke-up Clearing: Lift Installation & Commissioning: LW1 & LW2 – Installed and commissioned. LW3 – Fully operational from UG to the 51st floor. LW4A & LW1C – Fully operational from UG to the 65th floor. Customer Access: Down Takes, Risers & Branch Connections: Kitchen Ducts: Water Supply System: Typical Lobby Work: Servant Toilets: Podium & Painting: External painting (1st coat) completed up to the 64th floor. Final coat in progress. Podium level internal painting is ongoing. P1 to P7 flooring screed work is 85% complete; PU coating is 75% complete. Main Lobby & Amenities: Triple-height UG level main entrance lobby work has started. P8-level amenity area and the main entrance lobby are now operational. Tower A Staircases: |
Pilatus |
RCC slab completed till 61st floor & core area slab completed up to terrace slab
|
Blockwork: Internal blockwork is completed up to the 54th floor. Work on the 55th and 56th floor is currently in progress. Common area blockwork is finished from the P1 to the 52nd floor. Wall Finishing: Gypsum plastering is completed up to the 39th floor, and work is ongoing from the 40th to the 49th floor. Waterproofing: Waterproofing has been completed from the 9th to the 37th floor, and upper floors are currently in progress. Plumbing: Plumbing work is completed up to the 39th floor, with higher floors underway. Tiling: Bathroom tiling work is actively progressing across multiple floors. FAPA Typical Lobby: Completed up to the 34th floor & 35th to 45th floor work in progress. Firefighting Lobbies: Work in progress from the 9th to the 45th floor. Flat Firefighting Areas: Work in progress from the 9th to the 34th floor. Fire Riser Lines: Completed from B1 to the 45th floor. Electrical Work: Conducting work is completed from the 9th to the 53rd floor. Doors & Railings: Flat main door installations and internal railing work are currently in progress. Windows: Elevation window installation is ongoing. Lobby Finishing: Lobby flooring is completed from the 9th to the 45th floor, and dado and false ceiling work is in progress. Service Slab Railings: Railing installation on service slabs is 100% completed |
Zermatt |
RCC slab work completed till 7th floor
|
Excavation: Excavation work is 100% completed across the entire site. Shoring & Retention: Shore piling and capping beam work are completed, and soil retention work is currently in progress to ensure long-term stability. Rock Anchoring: Inclined rock anchoring has been successfully completed for the 1st, 2nd, and 3rd levels to strengthen the foundation. Raft & Slab Work: Tower Area: Tower raft casting is completed, including the non-tower section. RCC slab casting is completed from B2 level up to P6. Slab .7th typical level slab work completed & 8th slab work in progress. Non-Tower South Side: Slab casting is completed up to the UG (Underground) level, and work is progressing at the P2 level. |