Construction Updates – September 2026

Update as on 3rd September 2026

Construction Updates -September 2026

Update as on 3rd September, 2026

Titlis - OC received till the 64th Floor
100%
Pilatus - OC received till 45th floor
100%
Pilatus - 46th & above floor
75%
Zermatt
52%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis   OC received
Pilatus RCC slab completed & OC Received till 45th floor 

Blockwork: Internal blockwork is completed up to the 63rd floor. Common area blockwork is finished from the P1 to the 63rd floor and 64th & 65th  work in progress

Wall Finishing: Gypsum plastering is completed up to the 59th floor, and work is ongoing from the 60th to the 63rd floor.

Waterproofing: Waterproofing has been completed from the 9th to the 60th floor, and upper floors are currently in progress.

Plumbing: Plumbing work is completed up to the 62nd floor, with higher floors underway.

Tiling: Bathroom tiling work is actively progressing across multiple floors.

FAPA Typical Lobby: Completed up to the 63rd floor & 64th to 65th floor work in progress.

Firefighting Lobbies: Work in progress from the 9th to the 63rd floor.

Flat Firefighting Areas: Work completed from the 9th to the 62nd floor. 63rd floor work in progress.

Fire Riser Lines: Completed from B1 to the 62nd floor.

Electrical Work: Conducting work is completed from the 9th to the 62nd floor.

Doors & Railings: Flat main door installations and internal railing work are currently in progress.

Windows: Elevation window installation is ongoing.

Lobby Finishing: Lobby flooring is completed from the P2 to P7 and 9th to the 63rd floor, and dado and false ceiling work is in progress.

Service Slab Railings: Railing installation on service slabs is 100% completed

Flat Finishing – Flat marble flooring work in progress

Status – OC received up to 45th floor

Zermatt
RCC slab work completed till 27th floor

Excavation: Excavation work is 100% completed across the entire site.

Shoring & Retention: Shore piling and capping beam work are completed, and soil retention work is currently in progress to ensure long-term stability.

Rock Anchoring: Inclined rock anchoring has been successfully completed for the 1st, 2nd, and 3rd levels to strengthen the foundation.

Raft & Slab Work:

Tower Area: Tower raft casting is completed, including the non-tower section. RCC slab casting is completed from B2 level up to P6. Slab . core area casting completed till 33rd floor, 34th floor slab work in progress, Zone are slab completed up to 26th ,27th & 28th slab work in progress

Non-Tower South Side: Slab casting is completed up to the p6 level

Block Work  started from 7th to 20th floor , 21st & 22nd floor work in progress.

Waterproofing work in progress

Gypsum work completed from 7th to 13th floor , 14th to 17th floor work in progress.

Fire fighting work commenced for typical floor .

Screed work : completed from 7th to 15th floor,  16th Floor in progress.

concealed plumbing : completed unto 7th floor, above floor work in progress.

Concealed plumbing : 7th to 12th floor work completed & 13th floor work  in progress.

Flooring : flooring work completed upto 10th floor , 11th floor lobby & dado work completed

Fire Fighting – work commenced on typical floor .