Construction Updates – November 2020.

TITLIS
PILATUS

Tower A

Tower raft and Podium raft – 100 % completed
Basement – B1 complete, LG complete, UG  complete
Extended Podium in Tower A – 100% RCC completed upto Podium 8th Slab CC received till 52nd slab.

Tower B

Tower raft -100% completed.
Basement – B1 complete, LG complete, UG  complete, P1 complete, P2 complete, P3-Cental Core, Zone 2, Zone 4 complete & Zone 1, Zone 3 work in progress, P4-Cental Core, Zone 2, Zone 4 work in progress.

Civil work

TOWER A

• P1 to 45th floors for Zone 1,3 & 4, 50th floors for central core slab & 42nd floor zone 2 passage area casting done of Tower A.
• Slab shuttering & reinforcement work of 51st level of core area slab is in progress (Tower area).
• South & west side balance podium civil work up to P8 completed.
• Extended podium piling work is completed.

Receiving Station Area
• RCC completed upto P1 level, P2 – 70% completed, 30% work in progress,P3-50% reinforcement & shuttering working progress

Drop off Area
• 100% RCC work completed upto B1 level,o LG level, upto UG level.

TOWER B

• Micropile of 300 mm dia of Tower B  completed  and caping beam work is completed.
• Tower B upper level rock anchoring work in west line completed & North line upper leveland lower level is completed.
• North side and west up to 2nd level of Rock Anchor guniting work completed.
• Raft, Basements 1,LG level, UG level, P1 level & P2 level -100% RCC completed, P3 & P4 level work in progress

STP
• Raft -100% completed.
• Basement – B1 complete, LG work completed, UG complete, P1 complete, P2 complete, Tank pedestals work in progress

Clubhouse
• Raft -100% RCC completed
• Basement – B1 complete, LG complete, UG  complete, P1 complete,  P2 complete,  P3 complete, P4 complete, P5 complete, P6-complete, P7-work in progress.

Finishing work In Tower A

  • Block work & Gypsum- 9th to 39th floor complete
  • Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed.
  • Flat Toilet waterproofing work – 9th to 39th floor sold flat work completed.
  • External Painting Single coat – 9th to 39th floor completed for flats No 3,4,7,8; 9th to 38th floor completed for flats 1&2, Flat No. 5 & 6-9th to 39th floor work in progress,
  • Lift Installation & Commissioning – For LW1 A & B – Comissioning completed , For LW2 A & B – Commisioning completed.
  • Plumbing Downtakes – 9th to 38th completed -for flat no 3 -Study room, Junior , Common Toilet, Flat No 1&2 -All toilets,Flat No 4 & 5 common duct, Flat No 6 & 7 common duct, Flat No 8 -Study room, Junior , Common Toilet completed, 37th to 38th floor work in progress.
    For All kitchen ducts – 9th to 29th floor completed. 29th to 38th floor work in progress.
  • False ceiling-Lobby Area- Onlyframing work completed from 9th to 39th floor.
  • Lobby Area flooring-9th to 38th floor completed excluding 29th & 39th floor work is in progress.
  • HVAC work  –  Copper piping 9th to 39th floor completed in lobby area.
  • Servant toilet waterproofing work – 9th to 38th floor completed. Chemical coating completed from 9th to 39th floor completed.
  • Lobby Dado work- 9th to 35th floor excluding 29th & 33rd floor work completed for LW1 & LW2 area – 50 % area
  • Electrical conduiting & Choke up clearing work – 9th to 42nd floor completed.
  • Marble Flooring-9th to 39th Floor sold flat work in progress,
  • Window Installation : East elevation work in progress 9 to 39th floor
  • Internal Railing Work-9th to 23rd Floor work in progress,
  • External railing work: 20 -39th floor work in progress
  • Podium level internal painting in progress.
Tower Floor Details Detailed Updates
Titlis Completed upto 45th slab level RCC work done upto the 45th slab.

Finishing work done till the 39th storey.

Internal civil work completed upto the 45th floor.

External painting done upto 39 floors.

Slab shuttering work of 48th level slab in progress.

Electrical conduiting work completed till 42nd floor.

Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed

Flat Toilet waterproofing work – 9th to 39th floor completed

Lift Installation & Commissioning – For LW1 A & B – Comissioning completed , For LW2 A & B – Commissioning completed

Pilatus Completed Ground level Work Work completed for basement, lower ground and upper ground.

Raft work and RCC completed upto ground floor.