Construction Updates – September 2026
Update as on 3rd September 2026
Construction Updates -September 2026
Update as on 3rd September, 2026
% mentioned above is the current demand due as per the construction linked payment schedule
| Tower Name | Floor Details | Detailed Updates |
|---|---|---|
| Titlis | Â | OC received |
| Pilatus | RCC slab completed & OC Received till 45th floor |
Blockwork: Internal blockwork is completed up to the 63rd floor. Common area blockwork is finished from the P1 to the 63rd floor and 64th & 65th  work in progress Wall Finishing: Gypsum plastering is completed up to the 59th floor, and work is ongoing from the 60th to the 63rd floor. Waterproofing: Waterproofing has been completed from the 9th to the 60th floor, and upper floors are currently in progress. Plumbing: Plumbing work is completed up to the 62nd floor, with higher floors underway. Tiling: Bathroom tiling work is actively progressing across multiple floors. FAPA Typical Lobby: Completed up to the 63rd floor & 64th to 65th floor work in progress. Firefighting Lobbies: Work in progress from the 9th to the 63rd floor. Flat Firefighting Areas: Work completed from the 9th to the 62nd floor. 63rd floor work in progress. Fire Riser Lines: Completed from B1 to the 62nd floor. Electrical Work: Conducting work is completed from the 9th to the 62nd floor. Doors & Railings: Flat main door installations and internal railing work are currently in progress. Windows: Elevation window installation is ongoing. Lobby Finishing: Lobby flooring is completed from the P2 to P7 and 9th to the 63rd floor, and dado and false ceiling work is in progress. Service Slab Railings: Railing installation on service slabs is 100% completed Flat Finishing – Flat marble flooring work in progress Status – OC received up to 45th floor |
| Zermatt |
RCC slab work completed till 27th floor
|
Excavation: Excavation work is 100% completed across the entire site. Shoring & Retention: Shore piling and capping beam work are completed, and soil retention work is currently in progress to ensure long-term stability. Rock Anchoring: Inclined rock anchoring has been successfully completed for the 1st, 2nd, and 3rd levels to strengthen the foundation. Raft & Slab Work: Tower Area: Tower raft casting is completed, including the non-tower section. RCC slab casting is completed from B2 level up to P6. Slab . core area casting completed till 33rd floor, 34th floor slab work in progress, Zone are slab completed up to 26th ,27th & 28th slab work in progress Non-Tower South Side: Slab casting is completed up to the p6 level Block Work  started from 7th to 20th floor , 21st & 22nd floor work in progress. Waterproofing work in progress Gypsum work completed from 7th to 13th floor , 14th to 17th floor work in progress. Fire fighting work commenced for typical floor . Screed work : completed from 7th to 15th floor,  16th Floor in progress. concealed plumbing : completed unto 7th floor, above floor work in progress. Concealed plumbing : 7th to 12th floor work completed & 13th floor work  in progress. Flooring : flooring work completed upto 10th floor , 11th floor lobby & dado work completed Fire Fighting – work commenced on typical floor . |