Construction Updates -October 2023
Update as on 3rd October, 2023
Construction Updates – October 2023
Update as on 3rd October, 2023
Tower 1 OC received till the 51st floor!
Titlis - Till 51st Floor OC received
Pilatus
Zermatt
% mentioned above is the current demand due as per the construction linked payment schedule
Tower Name | Floor Details | Detailed Updates |
---|---|---|
Titlis |
Tower raft – 100% completed
Podium raft-100% completed. Basement – B1 complete, LG complete, UG complete. Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab. Center core CC completed till 58th floor. |
Tower 1 OC received till the 51st floor P1 to P8 podium floors completed, typical floor completed up to 62nd floor, 63rd level slab work in progress. Center core area casting including LMR completed up to top level. South & west side balance podium civil work up to P8 completed. Drop off Area – 100% RCC work completed upto B1 to P7 level & P8 level- 90% RCC work in progress. |
Finishing work |
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th to 51st level block work completed 90% & above floor work in progress . 40th to 51st gypsum work 75% completed. 52nd above floor block work in progress.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed & 40th to 51st work 85% completed. 52nd & above floor work in progress.
3) Flat Toilet waterproofing work – 9th to 49th floor all flats work completed.
4) External Painting Single coat completed up to 39th floor & 39B to 51st work in progress.
5) Project lift LW1 & LW2Â Installation & Commissioning completed, LW3 is now operational in full speed from UG to 51st floor. LW4 erection work started.
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress. kitchen ducts completed up to 39th floor completed & 39thB to 51st floor work in progress.
7) Typical lobby 9th to 40th floor work completed.41st to 51st floor work 90% completed.
8) Mid landing servant toilet completed up to 39th floor , toilet commissioned from 9th to 39th floor
9)Copper piping work completed in lobby area.
10) Marble flooring work in progress in sold flat upto 39th floor.
11) Electrical conducting & Choke up clearing work completed up to 51st floor.
12) Window Installation work 94% completed up to 39th floor, & 40th to 51st floor work 90% completed.
14)Internal Railing work 96% completed up to 39th floor & 40th above work in progress. ( 90% completed)
15) External railing work 95% completed till 39th floor & 40th above work 90% completed.
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress. ( 60% completed )
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started. 22) Project water supply line work completed 100% & building water distribution system commissioned. 23) possession handover of 70+ flats
|
|
Pilatus |
Tower raft -100% completed.
Basement – B1 complete, LG & UG complete, P1 to P7 slab casting done. STP installation work in progress . |
Raft, Basements 1 to P8 level -100% RCC completed, 1st floor service area work completed, 10th to 27th slab completed. 28th RCC slab work in progress. |
Finishing work | 1) Block work completed till 16th floor , 17th to 20th floor work in progress. 2) Gypsum work completed till 16th floor & 17th and above floor work in progress 3) Water proofing started from 9th to 11th floor. |
|
Zermatt |
Shore piling work
|
Excavation work started shore piling & capping beam work completed, soil retention work is in progress Excavation work 40% completed. Inclined rock anchoring 1st level work completed & 2nd level work in progress. |
Refer your friends to a home at Monte South and get rewards worth up to 1% of the new purchase. Your friend receives a discount of 0.5% on the new flat. It’s a win-win!