Construction Updates -November 2023

Update as on 5th November, 2023

Construction Updates – November 2023

Update as on 5th November, 2023

Tower 1 OC received till the 51st floor!

Titlis - Till 51st Floor OC received
100%
Pilatus
41%
Zermatt
16%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis
Tower raft – 100% completed
Podium raft-100% completed.
Basement – B1 complete, LG complete, UG complete.
Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab.
Center core CC completed till 58th floor.
Tower 1 OC received till the 51st floor
P1 to P8 podium floors completed, typical floor completed from 9th to 63rd floor, terrace slab work in progress.
Center core area casting including LMR completed up to top level.
South & west side balance podium civil work up to P8 completed.
Drop off Area – 100% RCC work completed upto B1 to P7 level & P8 level-  90% RCC work completed.
Finishing work
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th to 51st level block work completed 90% & above floor work in progress . 40th to 51st gypsum work 75% completed. 52nd above floor block work in progress.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed & 40th to 51st work 85% completed. 52nd & above floor work in progress.
3) Flat Toilet waterproofing work – 9th to 51st floor all flats work completed & 52nd  above floor work in progress.
4) External Painting Single coat completed up to 39th floor & 39B to 51st work in progress.
5) Project lift LW1 & LW2  Installation & Commissioning completed, LW3 is now operational in full speed from UG to 51st floor. LW4 erection work started.
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress.  kitchen ducts completed up to 39th floor completed & 39thB to 51st floor work in progress.
7) Typical lobby 9th to 40th floor work completed.41st to 51st floor work 90% completed.
8) Mid landing servant toilet completed up to 39th floor , toilet commissioned from 9th to 39th floor
9)Copper piping work completed in lobby area.
10) Marble flooring work in progress in sold flat upto 39th floor, 172 flat work completed , 39B to 51st floor marble laying completed 100% & 9th to 39th unsold floor work in progress.
11) Electrical conducting & Choke up clearing work completed up to 59th floor.
12) Window Installation work 94% completed up to 39th floor, & 40th to 51st floor work 90% completed.
14)Internal Railing work 96% completed up to 39th floor & 40th above work in progress. ( 90% completed)
15) External railing work 95% completed till 39th floor & 40th above work 90% completed.
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress. ( 60% completed )
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started.
22) Project water supply line work completed 100% & building water distribution system commissioned.
23) possession handover of 70+ flats
Pilatus
Tower raft -100% completed.
Basement – B1 complete, LG & UG complete, P1 to P7 slab casting done. STP installation work in progress .
Raft, Basements 1 to P8 level -100% RCC completed, 1st floor service area work completed, 10th to 29th Slab completed. 30th RCC Slab work in progress.
Finishing work 1) Block work completed till 21st floor , 22nd to 24th floor work in progress.
2) Gypsum work completed till 16th floor & 17th and above floor work in progress
3) Water proofing started from 9th to 12th floor.
Plumbing work in progress .
Zermatt
Shore piling work
Excavation work started 
shore piling & capping beam work completed, soil retention work is in progress
Excavation work 45% completed.
Inclined rock anchoring 1st & 2nd level work completed & 3rd level work in progress.

Refer your friends to a home at Monte South and get rewards worth up to 1% of the new purchase. Your friend receives a discount of 0.5% on the new flat. It’s a win-win!