Construction Updates -July 2023

Update as on 5th July, 2023

Construction Updates – July 2023

Update as on 5th July, 2023

Tower 1 OC received till the 51st floor!

Titlis - Till 51st Floor OC received
100%
Pilatus
36%
Zermatt
16%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis
Tower raft – 100% completed
Podium raft-100% completed.
Basement – B1 complete, LG complete, UG complete.
Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab.
Center core CC completed till 58th floor.
Tower 1 OC received till the 51st floor
P1 to P8 podium floors completed, typical floor completed up to 57th floor, 58th level slab work in progress.
Center core area casting completed up to 65th floor (Tower area) LMR bottom slab work in progress.
South & west side balance podium civil work up to P8 completed.
Drop off Area – 100% RCC work completed upto B1 to P7 level & P8 level-  RCC work in progress.
Finishing work
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th to 51st level block work completed 80% & above floor work in progress . 40th to 51st gypsum work 60% completed.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed & 40th to 51st work 85% completed.
3) Flat Toilet waterproofing work – 9th to 48th floor all flats work completed.
4) External Painting Single coat completed up to 39th floor & 39B to 51st work in progress.
5) Project lift LW1 & LW2  Installation & Commissioning completed, LW3 is now operational in full speed from UG to 51st floor.
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress.  kitchen ducts completed up to 39th floor completed & 39thB to 51st floor work in progress.
7) Typical lobby light fitting installation & in operational
8) Mid landing servant toilet completed up to 39th floor , toilet commissioned from 9th to 39th floor
9)Copper piping work completed in lobby area.
10) Typical Lobby Dado work completed on each floor up to 39th floor.
11) Electrical conducting & Choke up clearing work completed up to 51st floor.
12) Window Installation work 94% completed up to 39th floor, & 40th above work 90% completed.
14)Internal Railing work 96% completed up to 39th floor & 40th above work in progress. ( 90% completed)
15) External railing work 95% completed till 39th floor & 40th above work 90% completed.
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress. ( 60% completed )
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started.
22) Project water supply line work completed 100% & building water distribution system commissioned.
23) possession handover of 70+ flats
Pilatus
Tower raft -100% completed.
Basement – B1 complete, LG & UG complete, P1 to P7 slab casting done. STP installation work in progress .
Raft, Basements 1 to P8 level -100% RCC completed, 1st floor service area work completed, 10th to fire check slab completed. 22nd RCC slab work in progress.

Finishing work Block work completed till 13th floor , 14th floor work in progress.
Gypsum punning is in progress at 11th floor.
Zermatt
Shore piling work in progress- 214 pile completed out of 230 nos
Excavation work started 
Capping beam work in progress.
Excavation work 20% completed