Construction Updates – July 2022

Update as on 10th July, 2022

Construction Updates – July 2022

Update as on 10th July, 2022

Phase 1 OC received! (Till 39th floor)

Titlis - Till 39th Floor OC received
100%
Pilatus
23%
Zermatt
10%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis
Tower raft – 100% completed
Podium raft-100% completed.
Basement – B1 complete, LG complete, UG complete.
Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab.
Center core CC completed till 59th floor.
Phase 1 OC received
P1 to P8 podium floors completed, typical floor completed up to 47th floor, 48th level slab work in progress.
Center core area casting completed up to 59th floor (Tower area).
South & west side balance podium civil work up to P8 completed.
Drop off Area – 100% RCC work completed upto B1 top UG level. UG to  P3 level triple height entrance area casting completed 100%.P4 & P7- In 100% area slab casting done, P8 level-  RCC work in progress.
Finishing work
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th above block work started.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed.
3) Flat Toilet waterproofing work – 9th to 39th floor all flats work completed.
4) External Painting Single coat completed up to 39th floor.
5) Lift Installation & Commissioning completed.
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress.  kitchen ducts completed up to 29th floor completed & 30th to 38th floor work in progress.
7) False ceiling, Lobby Area, Sheet fixing completed up to 39th floor.
8) Lobby Area flooring completed up to 39th floor.
9)Copper piping work completed in lobby area.
10) Servant toilet tile work completed up to 39th floor.
11) Typical Lobby Dado work partly completed on each floor .
12) Electrical conducting & Choke up clearing work completed up to 42nd floor.
13) Window Installation work 94% completed up to 39th floor.
14)Internal Railing work in progress.
15) External railing work 95% completed.
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress.
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started.
22) Project water supply line work completed 100%.
23) possession started at site.
Pilatus
Tower raft -100% completed.
Basement – B1 complete, LG to P2 complete, STP installation work in progress .
Micropile of 300 mm dia of Tower B completed and caping beam work is completed.
Tower B upper level rock anchoring work in west line completed & North line upper level and lower level is completed.
North side and west up to 2nd level of Rock Anchor guniting work completed.
Raft, Basements 1,LG level, UG level, P1 to P8 level -100% RCC completed, service 1st floor completed, 10th & 11th floor RCC work in progress.

STP –
Raft -100% completed.
Basement – Basement – B1, LG to P2 complete. STP installation work in progress

Clubhouse –
Raft, Basements 1, LG level, UG level, P1 to P7 level -100% RCC completed, P8 level work in progress.

Zermatt
Construction not commenced yet