Construction Updates – December 2024
Update as on 6th December, 2024
Construction Updates – December 2024
Update as on 6th December, 2024
Titlis - OC received till the 64th Floor
Pilatus
Zermatt
% mentioned above is the current demand due as per the construction linked payment schedule
Tower Name | Floor Details | Detailed Updates |
---|---|---|
Titlis |
Tower raft – 100% completed
Podium raft-100% completed. Basement – B1 complete, LG complete, UG complete. Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab. Center core CC completed till 58th floor. |
Tower 1 OC received P1 to P8 podium floors completed, typical floor completed upto terrace level. Terrace above swimming pool & elevation work in progress. ( 95% completed) Center core area casting including LMR completed up to top level. South & west side balance podium civil work up to P8 completed. Drop off Area – 100% RCC work completed upto B1 to P7 level & P8 level- 90% RCC work completed. |
Finishing work |
1) Block work & Gypsum- 9th to 63rd floor completed , 64th floor in progress, 40th -51st gypsum work completed , 52nd above gypsum work 85% completed .
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed & 40th to 64th work completed.
3) Flat Toilet waterproofing work – 9th to 64th floor work in progress 85% completed.
4) External Painting Single coat completed up to 61st floor & final coat work in progress.
5) Project lift LW1 & LW2Â Installation & Commissioning completed, LW3 is now operational in full speed from UG to 51st floor. LW4A & LW1C is now operational in full speed from UG to 65th floor .
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress. kitchen ducts completed up to 51st floor completed & 52nd to 64th work in progress ( 85% completed)
7) Typical lobby 9th to 51st floor work completed and 52nd to 63th floor lobby tiling work 80% completed.
8) Mid landing servant toilet completed up to 39th floor , toilet commissioned from 9th to 64th floor work in progress.
9)Copper piping work completed in lobby area.
10) Marble flooring work completed till 62nd floor
11) Electrical conducting & Choke up clearing work completed up to 63rd floor.
12) Window Installation work 94% completed up to 9th to 64th floor
14)Internal Railing work 90 % completed.
15) External railing work 95% completed from 20th to 64th
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress. ( 85% completed ) & PU work 75% completed.
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started. 22) Project water supply line work completed 100% & building water distribution system commissioned. 23) UG level triple height main entrance lobby & p8 level amenity area is operational
24) Project water supply line work completed & Building water distribution system commissioned |
|
Pilatus |
Tower raft -100% completed.
Basement – B1 complete, LG & UG complete,P1 to P7 slab casting done. STP installation work in progress . |
Raft, Basements 1 to P8 level -100% RCC completed, 1st floor service area work completed, 10th to 47th Slab level casting completed. & 48th slab work in progress Core area slab completed till 53rd floor and 54th level slab in progress. |
Finishing work | 1) Block work completed till 44th floor & 45th floor work in progress. common area block work in progress from p1 to 44th floor. 2) Gypsum work completed till 32nd floor & 33rd floor work in progress. 3) Water proofing completed from 9th to 27th floor & above floor work in progress. Plumbing work completed till 30th & above work in progress. Bathroom tiling work in progress. FAPA typical lobby completed upto 34th floor Firefighting lobby work in progress from 9th to 35th floor, flat area work from 9th to 29th in progress, riser work 9th to 34th floor completed Electrical conducting work from 9th to 36th floor completed. Flat main door installation work 30% completed & internal railing work in progress Elevation window work in progress Lobby flooring work completed from 10th to 34th floor, dado & false ceiling is in progress Service slab railing fixing work 70% completed. |
|
Zermatt |
Excavation work
|
Excavation work completed shore piling & capping beam work completed, soil retention work is in progress Excavation work 100% completed. Inclined rock anchoring 1st ,2nd & 3rd level work completed. Tower c raft casting completed including non tower area tower foot print area RCC slab completed on B1,B2,LG & UGÂ & p1, p2, & p3 level slab work in progress. |