Construction Updates – October 2021

Construction Updates – October 2021

Phase 1 OC received! (Till 39th floor)

Titlis
90%
Pilatus
23%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis
Tower raft -100% completed, Podium raft-100% completed.
Basement – B1 complete, LG complete, UG complete.
Extended Podium of west & south side in Tower A-100% RCC completed upto Podium 8th Slab.
Center core CC received till 54th floor.
Phase 1 OC received
P1 to P8 podium floors completed, typical floor for 9th to 44th floor, above 45th floor civil work commenced
Center core area casting completed up to 54th floor (Tower area).
South & west side balance podium civil work up to P8 completed.
Receiving Station Area – RCC completed upto P1TO P6 LEVEL 100% completed,  At P7 – work in progress for  50% area.
Drop off Area – 100% RCC work completed upto B1 top UG level. UG to  P3 level triple height entrance area casting completed 100%. P4- In 100% area slab casting done, in remaining area shuttering and reinforcement work in progress. P5 level RCC work in progress 60 % area
Finishing work
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th above block work started.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed.
3) Flat Toilet waterproofing work – 9th to 39th floor all flat work completed.
4) External Painting Single coat – 9th to 39th floor completed for flats No 3, 4, 7, 8, 9th to 38th floor completed for flats 1&2, Flat No. 5 & 6-9th to 39th floor work in progress.
5) Lift Installation & Commissioning – For LW1 A & B , LW2 A & B – Commisioning completed.
6) Plumbing Downtakes – PVC SWR downtake completed for 9 to 39th floor, water supply riser completed for 9 to 39th floor, branch connection work completed for 9 to 25th floor. Podium level down take work in progress. For All kitchen ducts – 9th to 29th floor completed. 29th to 38th floor work in progress.
7) False ceiling-Lobby Area- Sheet fixing completed from 9th to 39th floor.
8) Lobby Area flooring-9th to 39th floor completed.
9) HVAC work – Copper piping 9th to 39th floor completed in lobby area.
10) Servant toilet  tile work – 9th to 38th floor completed.
11) Typical Lobby Dado work- partly completed on each floor for 9th to 39th floor.
12) Electrical conduiting & Choke up clearing work – 9th to 42nd floor completed.
13) Marble Flooring-9th to 39th Floor sold flat work in progress.
14) Window Installation :All elevation work completed 93% for 9 to 39th floor.
15)Internal Railing Work-9th to39th Floor work in progress, 81% completed.
16) External railing work: 20 -39th floor work 95% completed.
17) Podium level internal painting in progress.
18) Podium level civil work in progress.
19) South side ground parking area development in progress, West side road work in progress.
20) Internal road for customers from Fit-out possession is completed.
21) Tower A both staircase finishing is in progress.
22) Typical lobby light fitting installation completed and in operation.
23) UG level triple height main entrance lobby work started.
24) P8 level amenity area and landscape area finishing work started at site
25) 40th floor & above blockwork activity started.
26) Project water main supply line work completed 85%
27) Fit out possession started at site, client fit out interior work started at site
28) Flat main door fixing activity in progress.
Pilatus
Tower raft -100% completed.
Basement – B1 complete, LG complete, UG complete, P1 To P6 Slab casting dne and P7 lvl is in progress.
Old Club house Area – Basement to P7 lvl completed.
Infra-Batching Plant: Plant production started on 2/7/2015
Micropile of 300 mm dia of Tower B completed and caping beam work is completed.
Tower B upper level rock anchoring work in west line completed & North line upper level and lower level is completed.
North side and west up to 2 nd level of Rock Anchor guniting work completed.
Raft, Basements 1,LG level, UG level, P1 to P7 level -100% RCC completed, P8 level column reinforcement & casting work in progress.

STP –
Raft -100% completed.
Basement – Basement – B1, LG to P2 complete. STP installation work in progress

Clubhouse –
Raft, Basements 1, LG level, UG level, P1 to P7 level -100% RCC completed, P8 level  work in progress.