Construction Updates – December 2021
Update as on 4th December, 2021
Construction Updates – December 2021
Update as on 4th December, 2021
Phase 1 OC received! (Till 39th floor)
Titlis
Pilatus
% mentioned above is the current demand due as per the construction linked payment schedule
Tower Name | Floor Details | Detailed Updates |
---|---|---|
Titlis |
Tower raft – 100% completed
Podium raft-100% completed. Basement – B1 complete, LG complete, UG complete. Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab. Center core CC completed till 54th floor. |
Phase 1 OC received P1 to P8 podium floors completed, typical floor for 9th to 44th floor completed, above 45th floor civil work commenced Center core area casting completed up to 54th floor (Tower area). South & west side balance podium civil work up to P8 completed. Drop off Area – 100% RCC work completed upto B1 top UG level. UG to  P3 level triple height entrance area casting completed 100%.P4 & P6- In 100% area slab casting done, P7 level- RCC work in progress for 60% area |
Finishing work |
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th above block work started.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed.
3) Flat Toilet waterproofing work – 9th to 39th floor all flats work completed.
4) External Painting Single coat – 9th to 39th floor completed for flats No 3,4,7,8; 9th to 38th floor completed for flats 1&2, Flat No. 5 & 6-9th to 39th floor work in progress.
5) Lift Installation & Commissioning – For LW1 A & B , LW2 A & B – Commisioning completed.
6) Plumbing Downtakes – PVC SWR downtake completed for 9 to 39th floor, water supply riser completed for 9 to 39th floor, branch connection work completed for 9 to 25th floor. Podium level down take work in progress. For All kitchen ducts – 9th to 29th floor completed. 29th to 38th floor work in progress.
7) False ceiling-Lobby Area- Sheet fixing completed from 9th to 39th floor.
8) Lobby Area flooring-9th to 39th floor completed.
9) HVAC work – Copper piping 9th to 39th floor completed in lobby area.
10) Servant toilet tile work – 9th to 38th floor completed.
11) Typical Lobby Dado work- partly completed on each floor for 9th to 39th floor.
12) Electrical conduits & Choke up clearing work – 9th to 42nd floor completed.
13) Marble Flooring-9th to 39th Floor sold flat work in progress.
14) Window Installation: All elevation work completed 94% for 9 to 39th floor.
15)Internal Railing Work-9th to 39th Floor work in progress, 96% completed.
16) External railing work: 20 – 39th floor work 95% completed.
17) Podium level internal painting in progress.
18) Podium level floor screed work started for car parking.
19) South side ground parking area development in progress, West side road work in progress.
20) Internal road for customers from Fit-out possession is completed.
21) Tower A both staircase finishing is in progress.
22) Typical lobby light fitting installation completed and in operation.
23) UG level triple height main entrance lobby work started. 24) P8 level amenity area and landscape area finishing work started at site. 26) Project water main supply line work completed 85% 26) Fit out possession started at site, client fit out interior work started at site |
|
Pilatus |
Tower raft -100% completed.
Basement – B1 complete, LG complete, UG complete, P1 To P6 Slab casting done and P7 level is in progress. |
Micropile of 300 mm dia of Tower B completed and caping beam work is completed. Tower B upper level rock anchoring work in west line completed & North line upper level and lower level is completed. North side and west up to 2nd level of Rock Anchor guniting work completed. Raft, Basements 1,LG level, UG level, P1 to P7 level -100% RCC completed, P8 level column reinforcement & casting work in progress. STP – Clubhouse – |